Engineer reports: Phase II AMD/AML ROWs mostly secured; Chub Run and Phase IV sewer projects delayed awaiting approvals

Town of Nutter Fort Council · October 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The town's engineer reported ROWs secured for Phase II (28 of 34), an environmental assessment submitted to the Office of Surface Mining (10/23/25) and bid plans targeted by year-end; Chub Run contractor start is likely delayed to year-end and Phase IV awaits PSC and DEP approvals for a Sandy's Hardware connection.

The engineer provided a written report updating multiple infrastructure projects. For the Phase II AMD/AML project the report states right-of-ways are secured on 28 of 34 parcels and the environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025; the town is aiming to put the project out for bid by the end of the year.

The Chub Run Sewer Extension contractor was scheduled to begin around Nov. 1 but the engineer anticipated a likely delay to the end of the year. For the Phase IV Sewer Project the report said the town is awaiting Public Service Commission (PSC) and Department of Environmental Protection (DEP) approvals to connect to the Sandy's Hardware station. The update was provided via a written engineer's report; no motions or votes were taken on these items during the meeting.