Commission approves $1.499 million runway change order for Amelia Earhart Airport, contingent on FAA approval

Atchison City Commission · March 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved a $1,499,000 change order for runway construction delays tied to utility relocation; staff said 90% of the change order is expected to be covered by congressionally directed funding, leaving a local match of about $149,900, and approval is contingent on FAA review.

City staff presented a change-order request from the runway prime contractor for $1,499,000 to cover additional costs arising from utility-relocation delays, specifically a petroleum pipeline reroute. Mister McNamee explained the change order reflects increases in materials and labor since the original 2023 bid and noted the city already has congressionally directed funding (CDS) available to cover roughly 90% of the request.

“The county of funding would cover 90% of this change order request,” Mister McNamee said, and staff explained that the remaining local share is roughly $149,900. Staff also described prior payments and refunds tied to pipeline work that reduce the city’s incremental exposure; one staff comment estimated that after factoring those items the additional cost would be closer to about $34,140. The commission approved the change order but made the authorization contingent on FAA review and confirmation of federal funding.

Why it matters: the change order is intended to keep the runway project moving after utility-relocation delays; FAA review is required before the federal funding can be confirmed and the city is to proceed only after that confirmation.