Premier Lakes reported minimal red algae to be treated, completed most aeration repairs with two units requiring electrical work next week, recent dry-retention treatments, and a 'Zombie box' on back order to be installed at the Masters in about three weeks.

Dustin Hormann of Premier Lakes told the Board that crews identified minimal red algae in the lakes and scheduled treatment for the following day. He said dry-retention areas were recently treated and that aeration issues were corrected except for two units that need electrical work scheduled for the coming Monday or Tuesday.

Hormann added that the 'Zombie box' unit for the Masters is on back order and will be installed in roughly three weeks. Eric Long asked Charlie Krebs to obtain costs for replanting littorals behind 20859 Glen Eagles Lakes Drive (cord grass and arrowhead).