Park staff report six-inch PVC backwash pipe break, repairs and staffing updates at aquatic center

City of Pierre Park and Recreation Board · May 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported a break in a six-inch Schedule 80 PVC backwash pipe at the aquatic center, described repairs and next-step technical fixes, and confirmed the pool was refilled and staffing restored with a new concession manager and lifeguard supervisor in place.

Tipton provided a detailed operations update on the City of Pierre aquatic center, saying staff discovered and repaired a break in a six-inch Schedule 80 PVC pipe in the backwash system that affected both the recreation and 50-meter pools. Plumbers confirmed the pipe was properly supported and the team plans to set valves at a 45-degree angle next year to prevent water from trapping in the line.

Bryan reported the pool was refilled last Friday using fire hoses and that pumps and chemical balancing were completed the same day. Staffing was noted as restored: Cody returned from maternity leave, Pam Metzinger was introduced as the new concession manager, and Paula returned as lifeguard supervisor. Nick completed CPO training and provided backwashing instruction, and staff emphasized ongoing maintenance to reduce the risk of similar incidents.