Council OKs $121,550 change order for West Interceptor creek crossing work
Summary
The council approved change order #4 for the West Interceptor Segment 2 project to use flowable fill at a creek crossing because of seepage, adding $121,550 to the contract while staff said the project remains under the original estimate and on schedule.
Get email alerts on the Construction Change Order topic
No spam. Unsubscribe anytime.
Staff described a significant design modification at a low-water creek crossing on the West Interceptor Segment 2 project. A structural engineer recommended replacing a select fill with a flowable fill to form a more monolithic trench structure in an area experiencing seepage; staff requested council approval for change order #4 for $121,550 to make that modification.
Project staff said the original project estimate was about $4,066,000 and that after prior change orders the project remains below that estimate; a completion date (substantial completion) was noted as May 29, 2027 in the project schedule. Council approved the change order on a voice vote and staff emphasized the change was intended to protect the structure and avoid future repairs.