City awards South Collector wastewater construction contract to Santa Clara Construction for about $4.7 million
Summary
After evaluating 15 bids, staff recommended and council approved awarding RFB 73819 for the South Collector wastewater project to Santa Clara Construction; staff said the company scored highest on experience with large-diameter and fiberglass pipe and a 10% contingency was included in the project budgeting.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Council approved awarding RFB 73819 for the South Collector wastewater project to Santa Clara Construction Limited with an announced award amount of $4,714,829 and authorized the city administrator to finalize the contract. Utilities staff said 15 bids were received, with a range that included lows near $4.0 million and highs above $10 million; the procurement matrix weighted cost (50%) and qualifications/experience for large-diameter and fiberglass pipe installation, which staff said favored Santa Clara.
Gray Larman and project staff explained why the low bidder was not chosen: scoring combined cost and qualifications, and Santa Clara’s experience with similar pipe and deep trench conditions scored highest. Staff also described adding a 10% contingency to the construction total to accommodate likely field change orders. Council moved and carried the award by voice vote.