Citizen Portal

Get email alerts on the Abernathy Bridge topic

No spam. Unsubscribe anytime.

Contractor delays push Abernathy Bridge finish dates later; ODOT monitors costs and community impacts

Oregon Transportation Commission · May 7, 2026

Summary

ODOT staff reported progress at Abernathy (pier work, liquid shim, waterline relocations) but warned the contractor’s accepted schedule extends the finish date, and that ongoing delays will raise inspection, consultant and right‑of‑way costs; staff described outreach and support to affected businesses.

ODOT region staff updated the commission on Abernathy Bridge construction, showing progress on substructure work (completed crossbeam and pier work), installation of liquid shim for bearing plates, removal of conflicting girders for widening, and completion of two waterline relocations. Staff said the contract was modified (CCO‑50) to set a new contractual completion date of Oct. 21, 2026, and the contractor’s last accepted delivery plan extends beyond that with an industry schedule showing a potential finish of Oct. 19, 2027.

Staff said they are actively meeting with the contractor to seek schedule recovery but warned that if the contractor’s schedule holds, ODOT will need additional inspection, consultant and right‑of‑way funding to support the longer delivery. The project team described outreach to nearby businesses and city officials (Oregon City) and launched a “businesses are open” signage and partnership with chambers as mitigation. The commission pressed staff to enforce contract provisions and liquidated damages where appropriate; staff said contract administration is evaluating time requests and potential damages while seeking to hold the contractor accountable.

Staff will return with cost estimates for the additional inspection and schedule‑driven expenditures if the schedule does not improve.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source