Linn Valley council approved pay requisition No. 8 for BG Consultants totaling $662,317.22 and heard that the water construction project is roughly 43% complete; council also approved delegating near-term contracting authority for the system's next phases.

The Linn Valley City Council approved a pay requisition for the town's water project, awarding $662,317.22 to BG Consultants under pay requisition number 8.

Mayor (speaker 1) told the council the construction phase is about 43% complete and that the booster station is operational, adding that "testing and system integration is ongoing." Clerk (speaker 3) introduced the pay requisition and stated, "It's for BG Consultants in a total of $662,317.22." Council moved and adopted the pay requisition by voice vote.

The mayor said weather has caused some delays but that sanitation of the tower and additional meter purchases approved by USDA are moving forward. Council members indicated the project will require follow-up workshops to review connection requirements for properties served by the new system; no changes to those connection rules were adopted at this meeting.