Commission approves $310,496 change order adding sidewalks and street segments to 2026 project
Summary
The Commission approved Change Order #1 to the ADLC 2026 Street Improvements Project, increasing the contract by $310,496 to add Maple Street sections, a bypass exit lane, and 265 feet of sidewalk at Benny Goodman Park (part of the sidewalk funded by TIF).
Get email alerts on the Streets And Infrastructure topic
No spam. Unsubscribe anytime.
Trihydro engineer Sara Cline presented Change Order #1 to the 2026 Street Improvements Project, describing three added scope items: Maple Street work (Fourth to Seventh Street segments excluding certain intersections), a bypass exit lane from Park Avenue to Van Buren Street, and 265 feet of new sidewalk at Benny Goodman Park. The total contract increase cited was $310,496.00; the sidewalk portion will be funded from the Urban Renewal Agency Downtown TIF fund (available balance cited as roughly $17,000, with the sidewalk estimated at $15,771).
Commissioner Ed Beaudette asked about project oversight and whether the TIF funds would be used as a pass-through; Ms. Cline said the work will be performed under the existing contract specifications and that she will provide oversight while the pay application for the sidewalk portion comes from the identified TIF fund. CEO Bill Everett praised Trihydro and Hoffman’s contractor performance and asked the Commission to approve the change order. Commissioner Paul Smith moved to approve the change order; Commissioner Beausoleil seconded and the motion carried 5-0.