Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Project topic

No spam. Unsubscribe anytime.

Council pushes for firm PER timeline and flow verification on water project

Common Council, City of Bellevue, Idaho · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council asked public works to obtain a confirmed PER schedule from Merrick and to verify spring flows with a portable meter; staff said flow verification is needed to finalize disinfection and tie-in locations before design proceeds.

Council members pulled the water-project update from the consent agenda to ask for more detail about the preliminary engineering report (PER) and the project's schedule. Public works said the narrative portion from Merrick was missing from the packet; the mayor directed staff to obtain a firm date when the PER will be available and to provide it to the water-team meeting before returning to council.

Public works staff emphasized flow-rate verification as a critical near-term task. The city has secured a portable flow meter and planned to measure the flows of Spring 1, 2 and 3 so engineers can confirm whether a design target near 3 cubic-feet-per-second (CFS) is appropriate. "We want to be confident in our flow data," staff said, explaining that accurate field measurements would determine disinfection structure siting and whether additional collection improvements are needed.

Council asked for the PER to be circulated and for staff to identify any outstanding coordination with landowners or county officials. Staff also said initial route choices aim to avoid paved road disturbance by using easements and to minimize driveway disruptions during pipe installation; major technical choices remain subject to the PER and water-team review.