Project Hummingbird cleared technical reviews; GDOT traffic plans and escrow remain before land-disturbance permit
Summary
Project Hummingbird has finished variances and agency reviews; city staff said the project awaits GDOT finalization of traffic improvements (including a roundabout) and establishment of an escrow account for engineering costs before a land disturbance permit is issued.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
Staff told the council Project Hummingbird has completed required variance approvals, zoning reviews, fire marshal and building official checks and that the development agreement is finalized. The preliminary plat remains unchanged from its original submission and staff described the remaining step as administrative: finalizing GDOT traffic plans and the related escrow account for engineering costs required by the development agreement.
City staff said once traffic plans with GDOT are finalized and the escrow is established for engineering costs, the city will issue the land disturbance permit and site clearing can begin. Council members received the status update and the item was placed on the regular meeting agenda for formal action later that evening.