Playground closeout reported; committee asks staff to pursue wobble repair
Summary
Staff reported the playground installer completed the remaining punch-list (replacing a scuffed slide) and submitted a final invoice; the committee asked staff to follow up on a separate wobble in the Zip-line platforms that may require additional work.
Get email alerts on the Playground topic
No spam. Unsubscribe anytime.
Adam reported the playground installer completed the last punch-list item—a replacement of a scuffed slide section—and submitted a final invoice for contract closeout. “So that wraps up their outstanding items from that contract effort from last year,” Adam said, noting the installer’s invoice was submitted to close the contract.
Adam also reported a separate issue: Zip-line platforms have a slight wobble that the installer previously addressed with a temporary fix and may need a more robust post-installed anchor. The vendor indicated it would follow up but the work is outside the scope of the final closeout invoice; committee members said they wanted staff to continue pursuing a durable repair rather than deferring it. The committee agreed that the wobble should be fixed to avoid costlier repairs later.