Council accepts final payment and closeout for Kabbage parking garage; net deduction of $2,209
Summary
City Engineer Anna Allen reported final acceptance of repairs and replacements for the Kabbage parking garage, with a final pay application of $12,721.52 and a net change order of minus $2,209; council approved final acceptance unanimously.
Get email alerts on the Capital Project topic
No spam. Unsubscribe anytime.
City Engineer Anna Allen recommended final acceptance and approval of the final pay application for the Kabbage parking garage, reporting a final payment of $12,721.52 and a negative final change order of $2,209—meaning the contract netted an underrun.
Allen summarized that concrete repairs, replacement of staircases, and parking‑lot striping were completed and staff recommended approving the final pay and change order. Council members expressed satisfaction that the project was complete and noted the negative net change order as a favorable outcome. The council approved the resolution for final acceptance by a 6–0 vote.