Village plans to ramp up lateral lining and coordinate water main relays with road projects
Summary
Staff said lateral replacements (trenchless CIPP lining/pipe bursting) will increase in 2028 with an estimated 2028 spike to $600,000 for lateral work in targeted neighborhoods; main relay replacements will be timed with road reconstruction to avoid repaving conflicts.
Get email alerts on the Water And Sewer topic
No spam. Unsubscribe anytime.
Utility staff told trustees lateral replacement work will pick up in 2028, with trenchless methods such as CIPP lining and pipe bursting under consideration to reduce surface disruption. Staff identified neighborhoods (areas near Landbrook, 52nd Street, Silver Leaf and Raleigh Estates) as priorities for early work.
"When we talk about lateral replacements, we're proposing trenchless technology," staff said, and added the expected 2028 lateral replacement spike could be around $600,000 (targeted to dozens of homes rather than hundreds). Staff also emphasized timing main relay replacements to coincide with road reconstruction projects to avoid re-digging new pavement; they noted a multi-year, example project totaling $1,050,000 across two years for a station/engineering workload.