Commissioners press staff to slim cemetery headquarters plan after $13M GMP raised concerns
Summary
Commissioners expressed concern about a previously reported $13 million guaranteed maximum price for cemetery facilities and asked staff to return with smaller, lower-cost concepts and clearer funding details; parks staff said they will refine the design and funding approach.
Get email alerts on the Cemetery Project topic
No spam. Unsubscribe anytime.
Several commissioners said recent concepts for cemetery maintenance and headquarters were higher than they expected and urged staff to pare back scope and provide clearer funding options. One commissioner said the prior presentation caused public concern and that an office building might not be necessary for cemetery services, asking staff to explore lower-cost storage or maintenance alternatives.
Parks and recreation staff agreed to revisit the concept. Parks & Rec Director Stewart and project staff noted the $13,000,000 GMP included multiple buildings, roads, irrigation and demolition and that the team will explore flatter sites and consolidated designs to reduce earthwork and cost. "I think, there's some other things that we've discovered that when we come back, we'll maybe even try to consolidate more," one staff member said. Staff told commissioners they have not finalized timeline for new designs but will return with refined options and a dedicated work session when ready.