Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction topic

No spam. Unsubscribe anytime.

Bartlett High School renovation enters Phase 3; furniture deliveries and site work underway

Webster School Committee · July 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Business manager Ponto reported that Bartlett High School furniture deliveries are about two‑thirds complete, roofing and mechanical installations are in progress, and site work on the bus loop and walkways will continue through the summer toward a target move‑in within months.

Business Manager Ponto updated the committee on Bartlett High School construction and furnishing progress, saying surplus furniture has been claimed or disposed of and that new furniture deliveries are about two‑thirds complete. A designer is inspecting incoming furniture and administration is keeping contingency funds to address gaps between the original design and the installed pieces. Ponto said a room review will take place in August to identify any remaining items.

Ponto described ongoing construction work: metal roof panels and fascia installation at the penthouse, overhead mechanicals on the second floor, slab replacement preparations on the first floor, and site work including a binding coat on the bus loop. She said walkways around campus will be prioritized while summer school is in session and that move‑in is about four to five months away. The business manager added that punch‑list items are being tracked and that she is pleased with the overall progress.