Contractor outlines phased lane closures for bridge deck sealing; board approves

Goshen Board of Public Works and Safety · July 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Milestone Contractors told the board it will restrict lanes for phased deck sealing on multiple county bridges beginning July 27; the board approved lane closures July 27–Aug 1 by motion.

Zach Dean of Milestone Contractors told the board his company holds a contract with Elkhart County to perform deck sealing on several bridges, including County Road 17 over the Elkhart River and County Road 45 near the US-33 crossing.

"My name is Zach Dean with Milestone Contractors," he said, and described a phased approach in which outside lanes would be closed while traffic ran on the inside, then crews would flip to close the inside lanes. He said work was "starting on Monday, the 27th, running through Saturday with the intent of hopefully getting done by Friday." The board approved the lane closures for maintenance July 27 through Aug. 1 with a motion and unanimous voice vote.

The contractor listed the bridges affected and emphasized the phased lane restrictions are designed to maintain traffic flow during the work. No overnight closures or specific detour plans were recorded in the public minutes; staff indicated they would coordinate details.