Committee recommends Hickory & Ash valve and main replacement to Council at about $60,240
Summary
The Committee recommended approval to Village Council for a valve and main replacement at Hickory and Ash estimated at $60,239.68 plus contingency, voting unanimously in favor.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Public Service Committee voted to recommend the Hickory and Ash valve and main replacement project to Village Council. The motion, moved by Holfels and supported by Lockhart, carried with Ayes recorded as Lockhart, Trucks, Mondello and Holfels.
Staff reported an estimated project cost of $60,239.68 plus contingency. The Committee's recommendation will move the project forward for Council consideration; no further amendments were recorded at the Committee level.