Council approves Change Order No. 4 for Wastewater Treatment Plant SRF project
Summary
The Grand Ledge City Council unanimously approved Change Order No. 4 for the Wastewater Treatment Plant and Collection System Improvements Clean Water State Revolving Fund Project #5825-01; staff said the project remains on schedule and on budget.
Get email alerts on the Wastewater Treatment Project topic
No spam. Unsubscribe anytime.
Grand Ledge City Council voted unanimously July 13 to approve Change Order No. 4 for the Wastewater Treatment Plant and Collection System Improvements Clean Water State Revolving Fund Project #5825-01. City Manager Adam Smith told the council the project is on schedule and on budget, and recommended approval of the change order.
Doug Urquhart of Hubbell, Roth & Clark reviewed the technical elements of Change Order No. 4 for council members. The council approved the change order by motion; minutes state the motion carried unanimously.