Bond program manager reports savings on several projects, flags Tumalo and Redmond High overages

Redmond School District Board of Directors · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Chad Franke provided an HMK bond update showing projected savings on several projects totaling hundreds of thousands of dollars and noted the Tumalo project was approximately $700,000 over budget while Redmond High remained over budget.

Chad Franke briefed the board on progress and budget projections for HMK bond projects. He reported projected savings on several scopes: an estimated $315,000 savings on a Hartman reroof, about $100,000 savings on controlled entrances at Ridgeview and Tom McCall, generous projections near $300,000 for upstairs cooling and HVAC controls at Sage and Terrebonne, and approximately $800,000 projected savings for Obsidian (excluding soft costs). Athletics projects (four tracks, two turf football fields, RVHS tennis courts) were estimated to yield an aggregate savings of about $200,000.

Franke also reported two significant budget pressures: the Tumalo project was approximately $700,000 over budget and permits are moving forward there, and Redmond High remains over budget with final scopes still bidding. The transcript does not show the board taking an immediate budget action; the update was presented for information and oversight.