Public works: manhole lining, flow monitoring and centrifuge restart reported

City of Rainier City Council · December 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works Director Russ Reigel said manholes are scheduled to be lined the following week and flow monitoring is set for mid-December; Reigel also reported the wastewater-plant centrifuge is running again.

Public Works Director Russ Reigel updated the council that manholes in town are scheduled to be lined the following week and that flow monitoring at the wastewater plant is planned for mid-December as part of MAO-related work.

Reigel also reported the plant's centrifuge "is running again," and staff planned to install the city's Christmas tree in the A Street Plaza the next morning. No formal action was taken; these were operational updates to the council.