Staff updates water-treatment progress, raw-water line work and roundabout timeline; lift station excavation ongoing

Valley Center City Council · July 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported progress on the water treatment plant (filters, pump skids and backwash systems), raw-water-line installation along Seneca and the drainage ditch, advertisement for an 85th & Broadway roundabout in early August, and ongoing work on a lift station at Abilene.

Public-works staff updated the council on the water treatment plant: green sand filters, high-service pump skids, chemical mixing systems and a skid to clean nano filters are installed; crews are progressing on the raw-water-line project with line segments installed along Seneca and across the wastewater-treatment plant entrance.

Staff also said advertisement for the 85th and Broadway roundabout would be released the first week of August and letting would occur in mid-September, though actual construction could be delayed into the next year depending on how closures are handled. On the Abilene lift station, staff reported excavation and manhole-installation issues are being managed and that contractor coordination and financing remain to be finalized.