Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Staff updates water-treatment progress, raw-water line work and roundabout timeline; lift station excavation ongoing
Summary
Staff reported progress on the water treatment plant (filters, pump skids and backwash systems), raw-water-line installation along Seneca and the drainage ditch, advertisement for an 85th & Broadway roundabout in early August, and ongoing work on a lift station at Abilene.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Public-works staff updated the council on the water treatment plant: green sand filters, high-service pump skids, chemical mixing systems and a skid to clean nano filters are installed; crews are progressing on the raw-water-line project with line segments installed along Seneca and across the wastewater-treatment plant entrance.
Staff also said advertisement for the 85th and Broadway roundabout would be released the first week of August and letting would occur in mid-September, though actual construction could be delayed into the next year depending on how closures are handled. On the Abilene lift station, staff reported excavation and manhole-installation issues are being managed and that contractor coordination and financing remain to be finalized.

