City staff outline phased street reconstruction, limited closures and railroad coordination
Summary
Staff updated the committee on phases 1–3 of a major street reconstruction project, describing targeted local access, business coordination, and a timetable that anticipates contractor selection/map in August and substantial completion by February 2027.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
City staff provided the Bond Oversight Committee with a detailed status update on the multi‑phase street reconstruction project that has affected local access and businesses.
Staff said phase 1 work began in late 2023 and continued through 2024 with lane reductions and short‑duration closures; lessons learned shaped later phases. For phase 3, staff described splitting the work into sub‑phases to accommodate railroad coordination and a culvert replacement, limiting closures to preserve local access and adding signs to direct veterans services and truck traffic. Staff said they expect to receive a finalized contractor map in August and to coordinate with the railroad so major work can be completed in early 2027. The presentation highlighted outreach to property owners and businesses and the aim to keep restaurants and customers informed with signage and maintain access where possible.