Public works proposes new 2,000 sq ft garage; estimates $200 per sq ft, septic required
Summary
Public Works Director Ryan Welch described a proposed new 32x60 (about 2,000 sq ft) garage for the Public Works campus, with an estimated cost of $200 per square foot and an associated new septic system; additional storage for salt/sand and a hoop-house option were discussed.
Get email alerts on the Public Works Facilities topic
No spam. Unsubscribe anytime.
Public Works Director Ryan Welch told the Capital Committee that the existing salt shed has received some painting improvements but additional storage would be useful. Welch described a proposed new public works garage — approximately 32 by 60 feet, roughly 2,000 square feet — primarily bay space, and estimated construction costs at about $200 per square foot. He also said a new septic system would be required for the site.
The committee discussed interim storage options such as an additional shed or a hoop house for sand and salt. Welch was directed to refine plans and cost estimates so the project can be evaluated for inclusion in the town's capital program and potential bond funding.