Carlin flags urgent Oak Street lift station needs; estimate could rise above $8 million
Summary
City staff reported repeated failures at the Oak Street sewer lift station that create a two-hour response window versus a six-hour regulatory standard; Dowl Engineering will evaluate rehabilitation versus replacement and staff expect permitting/engineering to take about 18 months, with projected costs rising from $5.8 million to above $8 million due to inflation.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
City Manager Richard Braithwaite told the council that Oak Street’s sewer lift station is the system’s lowest collection point and has suffered multiple failures, creating only a two-hour response window before sewage begins backing up into basements—short of the six-hour response time required by state regulations. "This falls far short of the six-hour response time required by state regulations," Braithwaite said, noting the urgency of improvements.
Dowl Engineering has started a task order to determine whether rehabilitating the existing station or constructing a new facility nearby is the better option and to replace the force main to the treatment lagoons. Braithwaite said original estimates around $5.8 million may exceed $8 million with inflation and that permitting and engineering will likely take about 18 months, meaning construction would not begin until 2025 at the earliest.