City staff said Dowl Engineering is revising design and budget for the Arthur Springs water-main replacement; construction is anticipated next spring, the project is shovel-ready for federal funding, and inflation has increased estimated costs.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City Manager Richard Braithwaite told the council that the Arthur Springs water-main replacement project is progressing through design and budget reassessment with Dowl Engineering and that state regulatory permits are being coordinated. "The project will need comprehensive structural evaluation of the reservoir," Braithwaite said, and staff expect construction to begin next spring if permitting proceeds on schedule.
Braithwaite warned that inflation has raised projected costs and that staff are exploring Change Order #4 to keep work moving under existing contracts rather than starting new bids. He also said the Arthur Springs work currently qualifies as the city’s only shovel-ready project for available federal funding, and staff will present detailed budgets and bid packages as design and permitting advance.