Culvert replacement near completion; Lancelot Avenue and 2026 stormwater improvements to begin

Upper Allen Township Stormwater Authority · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the Upper Allen Township Stormwater Authority that the Bumblebee Hollow Road culvert replacement will be complete and open the following day and that Lancelot Avenue culvert work will begin next week, with stormwater improvements associated with roadway paving starting Thursday.

Township staff briefed the Upper Allen Township Stormwater Authority on the status of 2026 stormwater projects, reporting that the Bumblebee Hollow Road culvert replacement is essentially complete and will finish paving and guide-rail installation the following day. "That project, as of tomorrow will be complete," the township manager said, and staff confirmed water was flowing through the new culvert.

Staff also said the Lancelot Avenue culvert replacement will begin next week and that the broader 2026 stormwater improvements linked to roadway paving will begin on Thursday. The updates included a note that the property owner at the Bumblebee location had expressed concerns about water routing, but site checks by the engineer confirmed proper flow.