Board approves Pay Application #8 for Wall Street paving; project overruns revised downward

Village of Bloomington Board · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Delta 3 Engineering reported Wall Street is 75% complete; the board approved Pay Application #8 to JI Construction for $249,920, and Digman said estimated overrun is now about $55,000 after added village extras totaling approximately $140,000.

Delta 3 Engineering's update said Wall Street construction is about 75% complete, with cleanup and landscaping expected by June 6. Mark Digman reported that an earlier estimated overrun of approximately $70,000 (reported December) is now closer to $55,000 despite extra work added by the village.

The board approved Pay Application #8 to JI Construction for $249,920 (motion by Dennis Moris, seconded by Alan Mergen). Digman listed added items contributing to increased cost: a fill site (~$66,000), storm sewer on Spruce Road (~$15,000), paving on West Court (~$40,000), new water services/laterals (~$15,000), and additional tree removals (~$4,000), totaling roughly $140,000 in extras.