Delta 3 report flags aging wastewater plant equipment, recommends multi-year upgrades

Village of Bloomington Board · November 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Delta 3 presented a wastewater facility evaluation finding the plant at about 57% of design flow but facing new DNR limits (ammonia, E. coli, PFAS, chlorides, phosphorus); recommendations include replacing obsolete MCC, switching from chlorine to UV disinfection, new sludge tank, and blower improvements; construction is projected for 2028–29.

Jordan Fure of Delta 3 presented a draft Wastewater Treatment Facility Evaluation describing system capacity, regulatory drivers and recommended upgrades. He said the plant is operating at about 57% of design flow but was commissioned in 1983 and is not configured for newer DNR requirements including ammonia limits, fecal coliform/E. coli, PFAS, chlorides and total phosphorus. Key equipment noted as obsolete or in poor condition included the 1983 motor control center (MCC) with difficult-to-source parts, a high-wear comminutor, a generator that only powers blower #1 and is at the end of its useful life, and a sludge storage tank located in the floodplain in poor condition.

Delta 3 recommended replacing the MCC with variable-frequency drives, improving headworks with a mechanical screen and automatic bagger, converting from chlorine disinfection to UV, constructing a new sludge storage tank outside the floodplain, replacing blowers with sound enclosures and adding a dissolved-oxygen probe to regulate blower operation. Jordan outlined a timeline: final report in December 2025, facility plan in 2026, plans/specifications and grant applications in 2027, and construction likely in 2028–29. Delta 3 also noted a $5,000 reimbursement through Focus on Energy and will return in February 2026 to discuss priorities and costs for the facility plan.