All four streets paved; public works to verify quantities for special assessments

Saint Francis City Council · July 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works reported that Eden, Ellen, Vermont and Kansas have been paved and full access restored; remaining curb restoration and quantity verifications will precede special assessments.

The city's public works department reported that construction on four street-improvement projects — Eden, Ellen, Vermont and Kansas — has progressed and that "as of today, all 4 streets have been paved," restoring full access, the department head said.

Remaining work will focus on curb restoration over the next few weeks, after which staff will verify quantities and begin the special-assessment process. The department also reported completion of the drain-disconnect project and smoke testing; results will be compiled for a future presentation to council and staff will coordinate follow-up work with Milwaukee Water Works and MMSD where repairs were identified.