Commission hears updates on pavers, retaining wall and promenade schedule
Summary
Commissioners were told the paver project is installed, work on a Friends retaining wall ("Diana's wall") is ongoing with completion expected in early fall, and the promenade walk is targeted to begin October 1.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Commission staff reported progress on several park projects and the commission received the management report as an update.
"The paver project is installed, and everybody's seen the Friends stucco project," staff said, noting the buildings look "gorgeous." The commission heard that the Friends group will complete a retaining-wall section (referred to as the Friends Wall or Diana's Wall) and that the town is awaiting an engineer's report. Staff said the promenade walk construction is hoped to start on Oct. 1.
No formal action was taken; the projects were described as on schedule and staff said paperwork and procurement steps are underway to keep timelines on track.