Council approves $57,288.84 final payment for Gregory airport T-hangar

Gregory City Council · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Gregory City Council unanimously approved final payment of $57,288.84 to Vanderpol Dragline to close out the new airport T-hangar project, with the contractor citing federal funding delays and tight production schedules.

The Gregory City Council voted to pay the full final pay request of $57,288.84 to Vanderpol Dragline to close out construction of the new airport T-hangar. Motion to pay the full final pay request with no liquidated damages was made by Mayor Laura Petersen and seconded by Ashley Spinsby; the motion carried unanimously.

Bryan Vanderpol told the council that "the funding was excessively delayed by the federal government, and upon the notification of the funding award, the building then had a 14-week production time," which left little room for setbacks. Councilmember Alex Hamilton noted Vanderpol Dragline's prior work for the city and encouraged the company to bid on future projects. The payment completes the contractor's final invoice and allows the airport project to move into routine operations.