City administrator reports completed street work, cost estimate for overlay and wastewater concerns
Summary
City Administrator Chad Buckley reported Coronado Street completion, presented a mill-and-overlay estimate for South Douglas at $896.00 per square yard ($28,761.30), and said KDHE flagged elevated BOD levels at the wastewater treatment facility, noting truck-wash trailers dumping waste into the system.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City Administrator Chad Buckley reported at the Aug. 3 meeting that Coronado Street is complete and shared a mill-and-overlay estimate for South Douglas from Taylor to Truesdell at $896.00 per square yard (quoted total $28,761.30). "He received an estimate on the mill and overlay for South Douglas from Taylor to Truesdell at $896.00 a square yard or $28,761.30," the minutes state.
Buckley also reported a KDHE call regarding biochemical oxygen demand (BOD) levels at the wastewater treatment facility, explaining that "the trailers at the truck wash are dumping waste into our system which creates more bacteria than we are allowed." The minutes record the easement settlement with BLC Properties for $7,000.00 but do not specify next steps or corrective action for the wastewater issue within the excerpt.