Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Lead Service Lines topic

No spam. Unsubscribe anytime.

Council approves lead-service-line replacement agreement; estimate $25,000 per line

City of Mantorville City Council · May 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Engineer presented a Lead Service Line Replacement plan estimated at $25,000 per service line with reimbursement expected from the Minnesota Public Facilities Association; council approved the WHKS agreement for roughly 24 lines pending verification.

City Engineer Scott Huneke of WHKS presented plans and specifications for a Lead Service Line Replacement project estimating approximately $25,000 per service line and roughly 24 lines to be replaced. Huneke said costs will be reimbursed by the Minnesota Public Facilities Association and that about 10% of the costs are on the agreement paperwork.

Councilmember Jim Potter moved and Councilmember Jerrod Kappers seconded approval of the city’s agreement with WHKS to begin the project; the motion carried 5 ayes / 0 nays. Huneke noted some service lines still need verification before final counts and that reimbursement mechanisms will cover the per-line costs.

The approval authorizes staff and the consultant WHKS to proceed with project planning and verification of addresses; the council did not adopt an exact schedule or contractor at this meeting.