Construction updates: Intermediate South roof phases complete; additional testing at Walnut Street well
Summary
Staff reported Intermediate South roof phases 1 and 2 are complete, other roofing and masonry work is ~90% and scheduled for holiday period; well monitoring at 123 Walnut Street returned favorable results but follow-up testing was proposed due to a perched water table.
Get email alerts on the Construction Projects topic
No spam. Unsubscribe anytime.
Facilities staff provided site‑level updates across the referendum projects. At Intermediate South, roof phase 1 and gym phase 2 are complete; cafeteria and adjacent lower roofs are near completion with brickwork and control joints scheduled to be finished over the Christmas break. The contractor will stage equipment and clean the parking areas when construction activities conclude.
At 123 Walnut Street, staff reported that additional well monitoring tests were completed and results were favorable, but the team identified a perched water table isolating zones and recommended further testing. A proposal for the additional work is under review and staff said they plan to forward recommendations to district administrators within the next week.