Colchester board awards Porters Point renovation to PC Construction, authorizes letter of intent
Summary
On Sept. 18, 2025 the Colchester School District Board unanimously awarded the Porters Point Renovation/Addition Project to PC Construction and authorized Superintendent Amy Minor to sign a letter of intent, allowing preliminary work to begin while the full contract is finalized.
Get email alerts on the Porters Point Project topic
No spam. Unsubscribe anytime.
The Colchester School District Board of Education unanimously approved awarding the Porters Point Renovation/Addition Project to PC Construction at a special meeting on Sept. 18, 2025. Director Ben Yousey-Hindes moved to award the project and authorize the Business Manager to execute a contract contingent on an agreed final contract; the motion passed unanimously.
Architects and project consultants summarized the bidding process for the board. Polly Wheeler of Black River Design Architects said the district received five bids from pre-qualified contractors and "the bids were in a tight grouping, which is a good indication that the lowest bidder did not miss any significant details." John Hemmelgarn, also of Black River Design Architects, called it "great news" that bids came only from qualified, vetted contractors.
Superintendent Amy Minor told the board it would both approve a general contractor and authorize a letter of intent. "This letter, which has been vetted by the district's legal counsel, will allow the contractor to begin work while the full contract is finalized," Minor said. Director Nic Longo moved to authorize the superintendent to execute the letter of intent with PC Construction; that motion also passed unanimously.
Board members discussed bid totals in relation to the project's original and updated estimates, but the transcript does not include specific dollar amounts or a detailed bid breakdown. The meeting record notes five board members in attendance; the motions were recorded as passing unanimously. The board adjourned at 6:23 p.m.
Next steps noted by district staff include finalizing the contract with PC Construction and implementing the project schedule; the transcript does not specify start dates or dollar values for the contract.