Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Select Board: concrete walls done and framing planned for August at new fire station

Town of Jefferson Select Board · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Chair Norman Brown said the new fire station project finished pouring concrete walls on July 6, completed perimeter drainage and plans to begin framing the building on Aug. 3 with a crew from southern New Hampshire; interior utilities work is scheduled next.

The Select Board received a construction update for the new fire station: "We finished the concrete walls today (7/6/26) and stripped the last of the forms," Chair Norman Brown said. He added that perimeter drainage is complete and that plumbers and electricians will soon install interior piping and wiring; backfilling is underway and crews aim to pour the floor and start framing on Aug. 3 with a 15–20 person crew.

Brown described structural choices for the building: thicker 2x8 wall construction with a 14-foot clearance for the apparatus bays, and said the town's fire department moved equipment to allow use of the parking lot during the town parade. The board did not vote on additional spending, but members discussed scheduling and contractor logistics.