Contractor confirms foundation start target of August 17, says schedule intact
Summary
Despite a temporary work stoppage tied to a wetlands concern, the construction team told the committee the milestone to begin foundations remains set for August 17 and that weekly coordination with stakeholders continues.
Get email alerts on the Construction Schedule topic
No spam. Unsubscribe anytime.
A contractor representative told the committee the team lost roughly 2.5 weeks due to the wetlands issue but had access to an alternate field that allowed them to accelerate other work and maintain the overall schedule. The representative said, “That is still maintained for, for August 17,” describing the foundation start as the critical milestone that will drive subsequent work.
Committee members asked for a detailed foundation and footings timeframe and the contractor said a schedule (B6) is fully fleshed out and can be provided to members for review. Staff and contractor agreed to meet with interested committee members to walk through specific dates and escalation clauses for locked-in items like concrete.