Maintenance update: park project delayed, Kansas Ave street bids issued, Main Street gutter review planned
Summary
City maintenance reported flushing Zone 1 and monitoring flow/PSI, said the park project has been delayed by water‑tower work and storms, street bids for Kansas Avenue have been issued, and the council agreed to consult JEO about Main Street gutters and adjacent steps.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Maintenance staff reported that crews have started flushing Zone 1 while monitoring flow and PSI. Work on the park project has been delayed because of water tower work and storm damage, which also prevented pull‑through of wiring; the tops of the light pole bases will be grouted after plumbing and leveling are complete.
Street bids for Kansas Avenue have been sent out. Council discussed a missing cone on a gutter hole on Main Street caused by storms and agreed to consult JEO on Main Street gutters and to inspect the steps leading up to the sidewalks. Council thanked maintenance workers and community volunteers for storm cleanup.
No contract awards or firm timelines for the park project's remaining work were adopted at the meeting; the council instructed staff to consult JEO and provide updates on bids and repair scheduling.