Summary
Staff reported crews are ahead on multiple paving jobs and recommended bids: a $78,868 pipeline lining on County Road 26, a $135,638 crack‑sealing contract for two county roads, and a reclamite pavement-preservation project expected to extend service life by about five years.
Get email alerts on the Roads And Bridges topic
No spam. Unsubscribe anytime.
County engineering staff gave an update on roadwork and recommended several procurement items for upcoming action.
The road superintendent said paving crews completed work in the Copper Springs area, are prepping Springville parking lots, and expect to finish a federal-aid Kelly Creek Road project ahead of schedule. For capital projects, staff presented a Price Road Boring bid of $78,868 to install a pipeline liner on County Road 26, noting the trenchless approach would avoid a 2–3 month closure if the pipe were replaced conventionally.
Staff also recommended a crack-sealing contract from Remac Inc. for Oak Springville Road and Mountain View Road at $135,638 and described a reclamite preservation treatment for County Road 42 that staff expect will extend the hot-mix asphalt life by about five years. "This is the same company that did Gallant Road and Pinedale Road about 2 years ago," the engineer said in support of the crack-seal vendor's prior performance. Commissioners discussed timing (many projects to be completed before the end of September) and funding status; staff said purchase orders were secured for projects recommended for immediate award.