Committee signs off on multiple station-maintenance and safety projects in CIP
Summary
Council staff presented a set of level-of-effort projects — including female facility upgrades, life-safety system replacements, HVAC/electrical work, resurfacing and roof replacements — and the committee registered unanimous assent to advance them in the CIP.
Get email alerts on the Station Maintenance topic
No spam. Unsubscribe anytime.
A cluster of level-of-effort projects for Montgomery County Fire & Rescue was reviewed and advanced during the March 9 work session. Staff asked the committee to approve design and construction funding for gender-inclusive locker and restroom upgrades, modern life-safety (fire alarm) systems at several stations, HVAC and electrical replacements, resurfacing of paved station areas, and roof replacements across the station portfolio.
Ms. Farag said the female facility upgrades provide locker, shower and restroom modifications to selected stations to better accommodate both male and female staff and that work at specific stations (Station 8 and Station 16) has progressed. The life-safety systems project will fund modern fire alarm systems and had an increase in costs because FY31–32 were added to the planning schedule. Staff said Bethesda Station 20 is in construction and expected to be complete in June. Council staff recommended approval of the grouped level-of-effort items and the committee recorded a 3–0 assent.
Committee members asked for continued project scheduling clarity and how inter-project transfers (savings moved to police station work in a prior amendment) affect remaining balances. Staff said some savings were transferred in prior years and that they continually evaluate stations for future needs.