Committee recommends $32,000 appropriation for wastewater plant HVAC repairs after system contamination found

Finance, Organization and Personnel Committee · July 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Utilities Maintenance Manager Chris Tarr asked the committee to recommend a $32,000 appropriation from wastewater capital reserves (R2026‑36) to address newly discovered glycol contamination and other failures in the wastewater treatment HVAC system; the committee voted unanimously to recommend the appropriation to the City Council.

Chris Tarr, Utilities Maintenance Manager, told the committee that after contracting Precision Temperature Controls in January 2026 to replace the wastewater plant HVAC, crews discovered degraded glycol with an unbalanced pH causing equipment corrosion and failing phenolic valves. "Part of this would replace 500 gallons of glycol," Tarr said, and proposed adding a filter, associated piping, circulation with a cleaner called FERNOX, and replacing 10 phenolic valves as part of a single project.

Tarr asked the committee to recommend that the City Council adopt resolution R2026‑36 to appropriate $32,000 from the wastewater capital reserve for the HVAC replacement project. A council member moved and seconded the recommendation; the committee approved the appropriation unanimously. Tarr said combining the work into one project will make the repairs easier to complete and help stay within a limited budget.