Commission approves change order on University Park wastewater lagoon project
Summary
Commissioners approved Change Order No.1 for the University Park Wastewater Lagoon after staff explained the work required to avoid a closely located existing force main and the associated extra labor costs.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
The board reviewed Change Order No.1 for the University Park Wastewater Lagoon project. Public‑works staff explained that an unmarked force main was located closer than plans indicated, requiring slower excavation and extra labor to avoid utility strikes; that additional work accounts for part of the change‑order cost.
A commissioner moved to approve the change order and a second followed; the board voted to approve the change order. Staff said the adjustment keeps the project moving while avoiding damage to existing utilities.