Right-Trak Design hired for $8,050 structural evaluation of the highway garage
Summary
The Selectboard awarded a base contract of $8,050 to Right-Trak Design for a structural evaluation of the Town Highway Garage; funds will come from the Highway Building Improvement Reserve Fund.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Garage Building Committee received two bids for a structural inspection of the Town Highway Garage and recommended Right-Trak Design. The Selectboard awarded the contract to Right-Trak Design with a base contract amount of $8,050 to be paid from the Highway Building Improvement Reserve Fund.
The motion passed unanimously. The award allows the committee to proceed with the structural evaluation; staff indicated the contract will be managed through the Highway Building Improvement Reserve Fund and the committee's procurement process going forward.