TDOT gives procurement timeline for I‑24 Choice Lanes; some dates differ in presentation

Tennessee Department of Transportation (TDOT) · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

TDOT presenters laid out a procurement timeline including a September 21 proposal deadline, oral interviews Oct. 5–9, an expected commercial close in early/mid October, and a stated financial close target in July 2027; presenters gave different selection timing (August 26 vs. "anticipated in November") that attendees should note and confirm via posted Q&A.

TDOT presenters provided a sequence of upcoming procurement milestones for the I‑24 Southeast Choice Lanes solicitation but offered differing timeline references that firms should confirm via the posted Q&A and professional‑services mailbox.

Nick Kanazowitz said during the presentation that July 14 was the pre‑submittal meeting date, that proposals and selection events would follow and that a financial‑close deadline was expected around July 12 (stated for the financial close) with major construction oversight beginning in summer 2027. He also referenced a best‑value selection milestone (he cited August 26 in his slide narration).

Laura Doss gave the more detailed deadlines for proposers: "questions are due September 4 by 04:00, proposals are due September 21 by 04:00 and presentation/interviews are the week of October 5," and she said anticipated selection results would be posted in November. Doss directed firms to sign up for the consultant mailing list and said the department will post the presentation, recording and sign‑in sheet to the website.