Authority ratifies mayor's execution of WWTP Change Order No. 2 and approves Change Order No. 3 for KBC Construction

Bristow Municipal Authority · September 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Bristow Municipal Authority ratified the mayor’s execution of Change Order No. 2 and approved Change Order No. 3 for KBC Construction’s Wastewater Treatment Plant contract; the minutes list additions of $55,000 and $131,585.08 respectively and provide 'new amounts' that the minutes do not arithmetically reconcile to the original contract figure shown.

The Bristow Municipal Authority on Sept. 3 ratified the mayor’s execution of Change Order No. 2 and approved Change Order No. 3 for KBC Construction’s Wastewater Treatment Plant contract. Trustee Brian Peters moved for ratification of the mayor’s execution of Change Order No. 2 and Trustee Judd Johns seconded; the motion passed on a unanimous roll call. Trustee Peters then moved and Trustee Johns seconded approval of Change Order No. 3; that motion also passed unanimously.

The minutes state the original contract amount as $8,315,150. For Change Order No. 2 the minutes record an addition of $55,000 and list a 'new amount' of $8,611,583.20. For Change Order No. 3 the minutes record an addition of $131,585.08 and list a 'new amount' of $8,743,168.30. The minutes do not explain the discrepancy between the simple arithmetic sums and the 'new amount' figures recorded; the minutes present the amounts as written above without further clarification.

All present trustees voted Aye on both actions (Joe Church; Jeryn Fletcher; Heather Green; Judd Johns; Brian Peters; Jeff Roberts; Randy Witty). The minutes record the ratification and approval but no additional discussion about scope, schedule or funding source beyond prior lines referencing KBC Construction and loan/fund sources in the consent agenda items.