Elkton reports progress on Jackson Avenue waterline, water tower contract executed
Summary
Town officials said Jackson Avenue waterline installation will reach its segment end in about a week, then crews will connect service lines to businesses and move work to Route 340; the water tower contract is executed but construction has not started.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Public Utilities leaders told the Elkton Town Council on June 15 that installation of a water line on Jackson Avenue is progressing and is expected to reach the end of the current segment in about one week. After the main line is in place the contractor will begin connecting service lines to local businesses, and work will then transition to Route 340 at the Post Office.
Council members also recorded that the water tower contract has been executed but construction has not yet commenced; the contractor remains within the 12‑month performance period specified in the contract. Public Works additionally plans to excavate footers at the boat landing park for a shelter that is fully funded by the EDRC and will be provided at no cost to the Town.