Meade to seek bids for possible transformer replacement after oil test shows high hydrogen and methane
Summary
After oil samples from the North substation showed elevated hydrogen and methane, Council directed staff to put transformer replacement out to bid and await retesting before making a purchase decision; new transformers quoted at about $750,000, reconditioned at about $300,000.
Get email alerts on the Electric Substation topic
No spam. Unsubscribe anytime.
City Administrator Dean Cordes raised concerns about oil samples taken from the North substation that initially tested with high levels of hydrogen and methane. Cordes said samples were redrawn for additional testing and the council authorized putting a replacement transformer out to bid while awaiting the retest results; Council discussed price estimates of about $750,000 for a new transformer or $300,000 for a reconditioned unit.
The action does not commit the city to a purchase but moves the procurement process forward so options are available depending on the retest outcomes and final engineering review. Council indicated it would wait a couple of months for the additional lab results before making a final decision on acquisition and installation.