Village manager seeks $400,000 adjustment to complete Spring Street sidewalks project
Summary
Village staff requested increasing the Spring Street sidewalks project from $1.7 million to $2.1 million, with a $400,000 increase to be funded by county CHIPS allocations; staff said the corridor is about 65% complete and completing the next phase now is efficient.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Village public-works staff described a requested capital adjustment for the Spring Street sidewalks and paving project, asking trustees to increase the project from $1.7 million to $2.1 million.
The request includes a $400,000 addition from county CHIPS funding and county match commitments; staff said the village had the necessary estimates to finish the corridor and that Con Ed had no pending concrete work that would interfere with completion. "We got $400,000 from the county... so we got $400,000 from the county," staff said in describing the county's allocation and the village's plan to use its annual contractor to finish the work. Trustees asked whether the revised $2.1 million covered the entire stretch; staff clarified the scope and noted parts of the corridor had been completed already by utility work.