Carney Public Utilities Authority approves $6,675 change order for water-tower painting
Summary
The Board of Trustees of the Carney Public Utilities Authority approved Change Order No. 1 with Kimery Painting for Project CA-25-02 (ORWA RIG/ARPA Water Tower Improvements) in the amount of $6,675.00. The motion passed unanimously at the May 22, 2025 special meeting.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Board of Trustees of the Carney Public Utilities Authority on May 22 approved Change Order No. 1 with Kimery Painting for Project CA-25-02 (ORWA RIG/ARPA Water Tower Improvements) in the amount of $6,675.00. Committee member Greg Wolfe moved to approve the change order and Mayor Darrel Gibbs seconded; the board recorded the vote as "Yea: All; Opposed: None."
The change order was presented under the agenda item for Project CA-25-02. The agenda and motions are recorded in the minutes; the meeting began at 5:00 p.m. at the Carney Community Center and adjourned at 5:03 p.m. The minutes identify the project by its local code (CA-25-02) and the contractor as Kimery Painting.